Normalisasi Tiga Sungai Capai 61 Persen

Normalization on Three Rivers Reaches 61 Percent

The main problem is land acquisition

Normalization on three rivers, which conducted by Ciliwung-Cisadane Flood Control Office (BBWSCC), has reached 61 percent.

Those rivers are Ciliwung River, Pesanggrahan River, and Sunter River.

SDA Dept. Does Remapping on Land Acquisition Due to River Normalization

Jakarta Water Resources (SDA) Dept. Head, Teguh Hendrawan said, river normalization cannot be done up to 100 percent, because the land acquisition cannot be done on several lands.

"Normalization program have not reached 100 percent yet, but 61 percent. The main problem is land acquisition," he said at City Hall, Thursday (10/19).

He added, his side is still coordinating with BBWSCC related to river normalization program. Moreover, land acquisition authority is on Jakarta Provincial Government.

"Thus we need to coordinate continuously. Now we focus on normalization of these three locations," he closed.

Linked News
Popular News indeks
  1. 129 Motorcycle Parked Illegally in Daan Mogot Controlled

    access_time08-11-2026 remove_red_eye729 personBudhi Firmansyah Surapati
  2. Kampung Melayu Sports Facility Inaugurated to Tackle Brawls

    access_time06-11-2026 remove_red_eye684 personDessy Suciati
  3. Jakarta to Develop Its First Mangrove Botanical Garden

    access_time06-11-2026 remove_red_eye677 personDessy Suciati
  4. Aid for Fire Survivors at Pinus Elok Flats Has Been Distributed

    access_time06-11-2026 remove_red_eye648 personNurito
  5. Kampung Rambutan 1 Reservoir to Combine Flood Control with Public Recreation

    access_time06-11-2026 remove_red_eye647 personAldi Geri Lumban Tobing